Take a walk through the modular process by viewing the project photos below. Each step is outlined and they are listed in the order in which they take place.

Figure 1
|
This is step 1 which is the prepared lot
|
| |
Figure 2
|
This is the basement which has already been prepared and is waiting for the modular home to be placed on it. |
| |
Figure 3
|
The first piece of the home is then lowered onto the foundation |
| |
Figure 4
|
Here we see the back of the first section after it has been lowered onto the foundation |
| |
Figure 5
|
The second section (B) is layed on the foundation next to section 1. They are then joined together. |
| |
Figure 6
|
If the plans call for a second story, those pieces are layed on top of the base pieces and joined together. |
| |
Figure 7
|
After all the pieces are joined together, the roof and any remaining siding are put on the home. |
| |
Figure 8
|
Once all the pieces are assembled and the roof and siding are complete, the home is ready for interior finish work.
|